MM 7.9.2 Updation
MM version 7.9.2 released on 20.12.2014 by CEPT.
Pre-requisite
- MM 7.9.1 Should be Upgraded without any issues.
- Backup Should be taken before Upgradation, If any failure notice you can restore database.
Instruction
for Better Result Upgradation should be start after completion of work and Day end all the Moudles.
- MM 7.9.2 can Upgrade in the Middle of work, but all the module should be exit in both server and Client machine.
- Backup Should be taken just before upgradation.
- All the Booked eMO should be authorized in MM 7.9.1 itself, then Upgrade to Latest version of 7.9.2
Note: eMO Booked in MM 7.9.1, Could not authorize in MM 7.9.2. Once database Upgraded eMO Authorization can not done. CEPT also does not support for this issue. Just Cancel and Rebook the same in MM 7.9.2 to fix the Issue
Parcel Net MIS Version Up-Gradation
All the Modules should be upgraded in Sequence available in check list. if any error just raise the ticket with CEPT for Solution.
Before Run R Net Communication
After Upgrade the Point of Sale 7.9.2
- Just Login into Point of Sale to Update Version O 7.93
- Login into Despatch Just do Day begin and Day End to Update Desptach Version D7.9.2.
After Upgrade Postman 7.9.2
- Just Login Postman 7.9.2 once to update version information as P 7.9.2
BNPL Parcel Software if Available,
- Just Login once do daybegin and Dayend to Update Version information as B 7.9.2
- Execute ePayment Client to Update Version information
- then Execute R Net Communication to Update version C 7.9.2 and Transmit all the version information file to Central Server.
Note: Upgrade the Latest version in both server and Client machine, if any one machine not upgraded its failed to upgrade latest version information in Parcel Net Website.
THANKS TO : POTOOLS.BLOGSPOT.COM